Project Update 04.28.17

STEP

4 tanks were placed this week on Maryland, Oak, and New Jersey. County staff also acquired 4 more easements and conducted 4 more pre-construction meetings.

Community

1500 feet of pipe was installed by open cut and HDD method this week on Brick House, Kent, Harford, and Cecil; work to continue on Talbot Road, Kent Road, Wicomico, and finish out Penny Lane.

Transmission

Contractor performed night work at the Bay Bridge Airport this week. They installed about 500 feet of pipe in this area. Contractor will finish night work at the Airport by Wednesday May 3rd. Contractor will be moving the drill rig to the North of the Matapeake school area and setting a drill rig up at Pier One road.