Project Update- 08.11.17

STEP

Two tanks were installed this week on Tennessee Road by the contractor. Contractor will continue with tank installations on Oregon Road next week. County staff obtained 8 more easements bringing the total to 561 or 72% of all the easements.

Community

The contractor installed about 2173 lf of pipe by the open-cut and HDD method on Oregon, New Jersey, South Carolina and Utah Roads. The Contractor will continue installing spur line pipes at Brick House Road then RT 8 from Cecil to the Romancoke Pier.

Transmission

Contractor installed 40 lf of pipe at RT 8, crossing at the airport. Contractor completed asphalt patches at Davidson and Woodmoor Roads.  Next week contractor will complete RT 8 Crossing and tie in at the Airport; there will be a lane shift and construction equipment in the road. Please use caution, stay alert when passing through the lane shift and be prepared for some delays.