Day: April 5, 2018

Project Update 4.6.18

STEP Contractor installed 9 tanks on Talbot and Worcester Roads for the month.  The total number of tanks installed to date 234.  They also installed approximately 1300 lf of 1″ service line from previously installed tanks to the road on Maryland Road.  Contractor has…