Day: April 20, 2018

SKI Project Update 4.20.18

16-01 Contractor installed 5 tanks for the week on Wicomico Road.  They also ran about 500lf of 1″ service lines from the street to previously installed tanks.  The contractor also changed out 6 electrical meter boxes on New Jersey.  Electric meter modifications / change… Continue Reading “SKI Project Update 4.20.18”