SKI Project Update 4.20.18

16-01

Contractor installed 5 tanks for the week on Wicomico Road.  They also ran about 500lf of 1″ service lines from the street to previously installed tanks.  The contractor also changed out 6 electrical meter boxes on New Jersey.  Electric meter modifications / change outs will continue on New Jersey next week.  Drill shots will continue on Oak and Oregon Roads with tank installs on Wicomico.  County Staff has acquired 691 easements and has conducted 296 pre-cons to date.

16-02

Contractor installed about 45 curb stops for the week with about 900lf of 1″ service lines on Worcester, Wicomico, Kent, Talbot roads.   Curb stops will continue on Worcester next week.

16-03

Contractor is working at the treatment plant and is expected to finish that work next week.   Restoration will follow.