Project Update 04.27.18

STEP

Contractor installed 5 tanks on Talbot and Wicomico Roads for the week. The contractor also installed about 590lf of 1” service line from previously installed tanks to the street on Oregon Road. Contractor will continue installing tanks on Wicomico next week. Electrical connections will be made on New Jersey as well. County staff have acquired 695 easements and conducted 300 pre-construction meeting to date.

Community

Contractor installed about 50 curb stop connections to properties on Wicomico and Washington  this week; they will complete Wicomico and Cecil roads next week.

Transmission

Contractor still working on connection at treatment plant and punch list items.

 