Step
Contractor installed 5 step tanks for the week on Wicomico. They also ran about 565lf 1″ service lines from the property line to the step tank. The contractor also changed out 10 electrical meter boxes on Allegany. Electrical Meter Replace/ Electric Meter Modification will continue on Allegany next week. County Staff has acquired 696 easements and has conducted 314 pre-constructions to date.
Community
Contractor installed about 10 curb stops for the week with about 209lf of 1″ service lines on North Lake Road. Curb stops will continue on North Lake Road next week. Restorations to Phase A will continue.
Transmission
Contractor completed patching the roadway crossings at Queens Colony High Road and Kentmorr Road. Pavement restorations at the treatment plant have been completed