Month: June 2018

SKI Project Update 6.29.18

16-01 Step Contractor installed 7 step tanks for the week on Wicomico, Carroll and Pennick Roads. They also drilled 695lf of 1″ pressure sewer line from the property line to the step tanks.  Long Point and Romancoke Roads Electric Meter Installs will begin next… Continue Reading “SKI Project Update 6.29.18”

SKI Project Update 6.22.18

Step Contractor installed 7 step tanks for the week on Baltimore, Romancoke and Wicomico Roads. They also drilled 493lf of 1″ pressure sewer line from the property line to the step tanks on Tennessee Road. The Electric meter installs will begin again next week… Continue Reading “SKI Project Update 6.22.18”

SKI Project Update 6.15.18

  Step The contractor installed 5 step tanks for the week on Wicomico, Dorchester and Baltimore Roads.  They also drilled 629lf of 1″ pressure sewer line from the property line to the step tanks.  The contractor installed 6 electric meter replace / modification on… Continue Reading “SKI Project Update 6.15.18”

SKI Project Update May 2018

May rain fall recorded at the SKI office was over 10 inches.   STEP Contractor had a productive month in spite of the rain. The contractor installed 17 STEP tanks on Wicomico, Washington, and Kent Roads. They installed 35 Bio-tubes in previously installed tanks… Continue Reading “SKI Project Update May 2018”

SKI Project Update 6.1.18

Step Contractor installed 5 tanks for the week on Wicomico, Kent and Washington Roads.  They also ran 483lf of 1″ service lines from the street to previously installed tanks with bio-tube less pump.  The contractor installed 5 electric meter replace and 1 electric meter… Continue Reading “SKI Project Update 6.1.18”