Project was delayed due to an average of 6” of rainfall this week in Southern Kent Island. Step The contractor installed 3 STEP tanks for the week on Pennick and Ackerman Drive. They also drilled 304lf of 1″ pressure sewer line on Utah Road. … Continue Reading “SKI Project Update 7.27.18”
Step The contractor installed 5 step tanks for the week on Pennick Drive, Harford and Olive Branch Roads. They also drilled 515lf of 1” pressure sewer line on Utah Road. The contractor did yard restorations on Pennick Drive, Harford and Olive Branch Roads. The… Continue Reading “SKI Project Update 7.20.18”
Step The contractor installed 7 step tanks for the week on Pennick Drive, Olive Branch Road. They also drilled 917lf of 1″ pressure sewer line on Utah Road. The contractor did yard restorations on Pennick Drive and Olive Branch Road. The contractor will continue… Continue Reading “SKI Project Update 7.13.18”
16-01 The contractor installed 5 step tanks for the week on Pennick Drive, Olive Branch and Long Point Roads. They also drilled 735lf of 1” pressure sewer line on Utah Road. The contractor will continue drill shots on Utah Road next week. County Staff… Continue Reading “SKI Project Update 7.6.18”