SKI Project Update 7.6.18

16-01

The contractor installed 5 step tanks for the week on Pennick Drive, Olive Branch and Long Point Roads.  They also drilled 735lf of 1” pressure sewer line on Utah Road.   The contractor will continue drill shots on Utah Road next week.  County Staff has acquired 705 easements and has conducted 358 pre –construction meetings to date.

 

16-02

The contractor installed 19 curb stops for the week with 432lf of 1” service lines on New Jersey and Tennessee Roads.  The contractor also did yard restorations on Pennick, Carroll and Olive Branch Roads.  The contractor will continue curb stop installs on Tennessee next week.

 

16-03

The contractor and inspector continue to work on punch list for the Transmission line.

 