16-01 Step
Contractor installed 7 step tanks for the week on Wicomico, Carroll and Pennick Roads. They also drilled 695lf of 1″ pressure sewer line from the property line to the step tanks. Long Point and Romancoke Roads Electric Meter Installs will begin next week. The contractor will continue drill shots on Tennessee Road next week. County Staff has acquired 705 easements and has conducted 351 pre-construction meetings to date.
16-02 Community
The contractor installed 17 curb stops for the week with 365lf of 1″service lines on New Jersey Road for the week. The contractor will continue curb stop installs on New Jersey Road next week.
16-03 Transmission
The contractor performed continuity testing on transmission main tracer wire. The contractor continued working on the trail restoration from Carroll Road North to the golf course entrance. The contractor and the inspector continued working on various transmission main project punch list items