SKI Project Update 6.29.18

16-01 Step Contractor installed 7 step tanks for the week on Wicomico, Carroll and Pennick Roads. They also drilled 695lf of 1″ pressure sewer line from the property line to the step tanks.  Long Point and Romancoke Roads Electric Meter Installs will begin next…