SKI Project Update May 2018

May rain fall recorded at the SKI office was over 10 inches.   STEP Contractor had a productive month in spite of the rain. The contractor installed 17 STEP tanks on Wicomico, Washington, and Kent Roads. They installed 35 Bio-tubes in previously installed tanks…