SKI Project Update 6.22.18

Step

Contractor installed 7 step tanks for the week on Baltimore, Romancoke and Wicomico Roads. They also drilled 493lf of 1″ pressure sewer line from the property line to the step tanks on Tennessee Road. The Electric meter installs will begin again next week on Long Point and Romancoke Roads. The contractor will continue drill shots on Tennessee Road next week. County Staff has acquired 703 easements and has conducted 344 pre-construction meetings to date.

Community

The contractor installed 8 curb stops for the week with 170lf of 1″ service lines on Elm Street, Virginia and Tennessee Roads. The contractor also did roadside restorations on Wicomico and Margaret Roads. The contractor will begin curb stop installs on New Jersey Road next week.

Transmission

The contractor and inspector continue to work on punch list for Transmission line.