Step
The contractor installed 5 step tanks for the week on Wicomico, Dorchester and Baltimore Roads. They also drilled 629lf of 1″ pressure sewer line from the property line to the step tanks. The contractor installed 6 electric meter replace / modification on Long Point and Olive Branch Roads. Electric meter installs will continue next week on Long Point and Romancoke Roads. The contractor will continue drill shots on Tennessee Road next week. County Staff has acquired 703 easements and has conducted 339 pre-construction meetings to date.
Community
The contractor installed 15 curb stops for the week with 346lf of 1″ service lines on Utah Road. The contractor will begin curb stop installs on Elm Street next week.
Transmission
The contractor and inspector are working on punch list for Transmission line.