Project was delayed due to an average of 6” of rainfall this week in Southern Kent Island. Step The contractor installed 3 STEP tanks for the week on Pennick and Ackerman Drive. They also drilled 304lf of 1″ pressure sewer line on Utah Road. … Continue Reading “SKI Project Update 7.27.18”