Month: August 2018

SKI Project Update 8.31.18

Step The contractor installed 4 STEP tanks for the week on Penny Lane, Long Point, Claiborne, Allegany Roads. They also drilled 692lf of 1″ pressure sewer line on Wicomico Road. The contractor worked on yard restorations and cleanup on North Lake and Wicomico Roads. … Continue Reading “SKI Project Update 8.31.18”

SKI Project Update 8.24.18

Step The contractor installed 6 STEP tanks for the week on Long Point Road. They also drilled 211lf of 1″ pressure sewer line on North Lake Road and Bay Drive.  The contractor worked on yard restorations and cleanup on Long Point Road.  Next week,… Continue Reading “SKI Project Update 8.24.18”

SKI Public Hearing Series Presentation 08.21.18

SKI- Public Hearing Series Presentation- 08.21.18

SKI Project Update 8.17.18

Step The contractor installed 6 STEP tanks for the week on Long Point and Claiborne Roads. They also drilled 619lf of 1″ pressure sewer line on North Lake Road.  The contractor worked on yard restorations on Long Point Road.  Next week, weather permitting the… Continue Reading “SKI Project Update 8.17.18”

SKI Project Public Hearing Notice

The County Commissioners of Queen Anne’s County will hold a series of three (3) public hearings beginning at 6:00 pm on Tuesday, August 21, 2018 at the Kent Island High School’s auditorium located at 900 Love Point Road, Stevensville, Maryland 21666 Below are links… Continue Reading “SKI Project Public Hearing Notice”

SKI Project Update 08.10.18

Step The contractor installed 3 STEP tanks for the week on Claiborne and Long Point Roads.  They also drilled 646lf of 1″ pressure sewer line on North Lake Road.  The contractor worked on yard restorations on Long Point Road.  Next week, weather permitting the… Continue Reading “SKI Project Update 08.10.18”

SKI Project Update 08.06.18

STEP The contractor installed 21 STEP tanks for the month. They also replaced or modified 25 electric meters, and directional drilled 2561lf of 1” service line to previously installed tanks. The work completed to date, equates to about 35% of the total job with… Continue Reading “SKI Project Update 08.06.18”