Step

The contractor installed 6 STEP tanks for the week on Long Point Road. They also drilled 211lf of 1″ pressure sewer line on North Lake Road and Bay Drive.  The contractor worked on yard restorations and cleanup on Long Point Road.  Next week, weather permitting the contractor will continue drill shots on Bay Drive. The contractor installed 5 electric meter replacement / modifications on Pennick Drive and Carroll Road this week.  The contractor plans to continue with electric meter installs on Pennick Drive, Penny Lane and Howard and Carroll Roads next week.   County Staff has acquired 727 easements and has conducted 404 pre-construction meetings to date.

 

Community

The contractor installed 29 curb stops with 570lf of 1″ service tubing on South Carolina and Beach Roads for the week.  The contractor will continue curb stop placements on South Carolina Road and Oak Street next week. 

 Transmission

No project activity.

 

 

 

 

 

 