Day: August 17, 2018

SKI Project Update 8.17.18

Step The contractor installed 6 STEP tanks for the week on Long Point and Claiborne Roads. They also drilled 619lf of 1″ pressure sewer line on North Lake Road.  The contractor worked on yard restorations on Long Point Road.  Next week, weather permitting the…