SKI Project Update 8.24.18

Step The contractor installed 6 STEP tanks for the week on Long Point Road. They also drilled 211lf of 1″ pressure sewer line on North Lake Road and Bay Drive.  The contractor worked on yard restorations and cleanup on Long Point Road.  Next week,… Continue Reading “SKI Project Update 8.24.18”