SKI Project Update 8.31.18

Step The contractor installed 4 STEP tanks for the week on Penny Lane, Long Point, Claiborne, Allegany Roads. They also drilled 692lf of 1″ pressure sewer line on Wicomico Road. The contractor worked on yard restorations and cleanup on North Lake and Wicomico Roads. … Continue Reading “SKI Project Update 8.31.18”