SKI Project Update 8.17.18

Step

The contractor installed 6 STEP tanks for the week on Long Point and Claiborne Roads. They also drilled 619lf of 1″ pressure sewer line on North Lake Road.  The contractor worked on yard restorations on Long Point Road.  Next week, weather permitting the contractor will continue drill shots on North Lake Road. The contractor installed 5 electric meter replacement / modifications on Pennick Road this week.  The contractor plans to continue with electric meter installs on Pennick and Carroll Roads next week.  County Staff has acquired 722 easements and has conducted 403 pre-construction meetings to date.

 

Community

The contractor installed 15 curb stops with 352lf of 1″ service lines on Oregon, Beach and Romancoke  Roads for the week.  The contractor will continue curb stop placements on South Carolina and Beach Roads next week.  The contractor worked on shoulder restoration this week on Tennessee Road.

 

Transmission

The contractor and inspector continue to work on the on-going punch list items.

 