SKI Project Update 7.13.18

Step The contractor installed 7 step tanks for the week on Pennick Drive, Olive Branch Road. They also drilled 917lf of 1″ pressure sewer line on Utah Road. The contractor did yard restorations on Pennick Drive and Olive Branch Road. The contractor will continue… Continue Reading “SKI Project Update 7.13.18”