Step

Contractor installed 4 tanks for the week on Wicomico, Kent and Dorchester Roads.  They also ran 238lf of 1″ service lines from the street to previously installed tanks.  The contractor also changed out 11 electrical meter boxes on Long Point and Allegany.   Electric meter modifications / change outs will continue on Long Point and Allegany next week.   Drill shots will continue on South Carolina Road with tank installs on Washington Road.  County Staff has acquired 701 easements and has conducted 321 pre-cons to date.

 

Community

Contractor installed about 20 curb stops for the week with about 423lf of 1″ service lines on North Lake and Utah Roads.  Curb stops will continue on Utah Road next week.

 

Transmission

Contractor is working on calibrating the flow meter at the waste water treatment plant.  Asphalt Paving Restoration to continue within Romancoke on the Bay.