SKI Project Update 9.14.18

Step

The contractor installed 2 STEP tanks for the week on Pennick Drive and Long Point Road.  They also drilled 371lf of 1″ pressure sewer line on Wicomico Road.   Next week, weather permitting the contractor will continue drill shots on Wicomico Road.  This week, the contractor worked on yard restorations on Long Point Road, Penny Lane and Pennick Drive.  The contractor installed 05 electric meter replacement / modifications on Pennick Drive and Olive Branch Roads this week.  County Staff has acquired 734 easements and has conducted 408 pre-construction meetings to date.

 

Community

The contractor installed 18 curb stops and 367lf of 1″ service tubing on Maryland Road for the week.  The contractor will continue curb stop placements next week on Bay Drive, Penny Lane, Romancoke and Virginia Roads.

 

Transmission

No project activity.

 

 