SKI Project Update 4.12.19

STEP

This week the contractor completed 2 house connections to the Public Sewer System on Maryland and Oregon Roads and currently working on 1 additional house connection located on Maryland Road.  The contractor installed 1 STEP Tank this week on South Carolina Road.  Three pump assemblies were installed to a previously installed BIO tubes in addition to installing 57LF of 4”gravity sewer line to the individual homes.  The contractor completed 5 septic tank abandonments this week.  Three control panels were installed by the contractor along with 372LF of 1” electrical conduit and 362LF of 1” pressure sewer line drilling.   Ten electric meter replacements / modifications were installed by the contractor this week on Bay Drive , South Carolina and Romancoke Roads.  The contractor also worked on yard restorations throughout the Kent Island Estates Community.  Next week, the contractor will continue with 1” drill shots and priority list house connections.  The contractor should also begin posting new signs for upcoming house connection locations next week.

  • County staff has performed 534 pre- construction meetings and acquired 754 easements to date.
  • County staff has performed 5 post-construction meetings to date.
  • The contractor has installed 447 STEP tanks to date.
  • The contractor has connected 48 houses to the public sewer system to date.

4.12.194.12.19 II                                                    

 

%d bloggers like this: