SKI Project Update 11.1.19

STEP

This week, the contractor completed 5 Public Sewer house connections and installed four STEP tanks on Queen Anne Road.  Five STEP assemblies with pumps were installed on Queen Anne Road in addition to 92LF of 4” gravity sewer line installed to those individual homes.  The contractor completed 6 septic tank abandonments.  Five control panels were placed by the contractor along with the installation of 1,269LF of electrical conduit and 1″ pressure sewer line.  The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue utility operations on Queen Anne Road, additional locations will be posted; drilling 1” service lines, installing STEP tanks and house connections.  County staff has performed 623 pre- construction meetings and acquired 756 easements to date.

  • County staff has performed 30 post-construction meetings to date.
  • The contractor has installed 527 STEP tanks to date.
  • The contractor has connected 190 houses to the public sewer system to date.
  • 208  QA flowable.jpgeb9de51c-9b0c-438c-be82-123f32f31b0e
%d bloggers like this: