The word for the week has been RAIN.

STEP

Through all the rain this week the contractor installed 3 tanks on Maryland and New Jersey. County staff has acquired 379 easements to date; work to continue on New Jersey after the Holiday.

Community

Contractor installed approximately 1500 lf of pipe by the open cut and direction drill method on Talbot, Wicomico, and Caroline Roads this past week; work will continue on Wicomico after the Holiday.

Transmission

Contractor installed about 2000 lf of pipe, North of Blunt Marsh Lane, by the HDD method. The contractor will be moving the drill to the next drill site across for the Bay Bridge Airport, this will be after the Holiday.