Project Update 06.02.17

This month has been wet!!!

STEP

16 tanks were installed this month on Maryland and New Jersey Roads. This brings the total number of tanks installed to 66. Another 29 easements were signed this week, 43 for the month, to bring the total to 419. This is about 54% of the total project.

Community

Contractor installed 10,300 lf of pipe by the open cut and directional drill method for the month. To this point 37% of the total pipe has been installed with 26% of the contract time used.

Transmission

Contractor installed 4500 lf of pipe by the open cut and directional drill method for the month. To this point 58% of the total pipe has been installed with 26% of the contract time used.