Day: June 2, 2017

Project Update 06.02.17

This month has been wet!!! STEP 16 tanks were installed this month on Maryland and New Jersey Roads. This brings the total number of tanks installed to 66. Another 29 easements were signed this week, 43 for the month, to bring the total to… Continue Reading “Project Update 06.02.17”