Project Update 06.30.17

STEP The contractor installed 19 tanks for the month, bringing the total installed to 85. That is about 10% of the tanks to be installed. Staff continues to acquire easements and meet with homeowners for pre-tank installations. Tanks will continue to be installed on… Continue Reading “Project Update 06.30.17”