Day: March 2, 2018

Project Update 03.02.18

STEP Contractor installed 5 tanks for the month and ran 1403lf of 1” pressure pipe from 13 previously installed tanks to the street. This brings the number of tanks installed to 225 to date. This equates to 28% of the contract price paid out…