Project Update 03.29.18

STEP Contractor installed 2 tanks on Talbot Road this week. They also installed 1” service lines to previously installed tanks on Maryland Road. Tanks will continue to be installed on Talbot next week. County staff have acquired 682 easements to date and performed 281…