Project Update 03.29.18

STEP

Contractor installed 2 tanks on Talbot Road this week. They also installed 1” service lines to previously installed tanks on Maryland Road. Tanks will continue to be installed on Talbot next week. County staff have acquired 682 easements to date and performed 281 pre-construction meetings with homeowners.

 Community

Contractor installed 40 + curb stops this week on Talbot Road. They will continue next week on Talbot to Somerset. Contractor also completed leak testing in phase A of the project.

 Transmission

Contractor completed pressure and leak testing for the entire transmission main this week. Contractor also cored into the wet well at the Waste Water Treatment plant in preparation to install final piping.