STEP
Contractor installed one step tank on Talbot RD. Inclement weather has slowed down progress for the week. County staff has aquired 679 easements(88%) to date. Contractor to continue installing tanks on Talbot.
COMMUNITY
Contractor placed ten curb stops on Baltimore Road for the week. Next week contractor will finish services on Route 8 and continue installing curb stops on Dorchester Road.
TRANSMISSION
Contractor finished pressure testing on main lines. Started continuity testing on the main lines. Contractor will continue continuity testing. Also, will be coring wet well at treatment plant next week.