Project Update- 06.16.17

STEP

4 Step Tanks were installed this week on Maryland and New Jersey Roads. Contractor will continue on these roads next week. County staff acquired 7 more easements and held 8 pre-construction meetings. We have about 63% of the total number of easements.

Community

Contractor installed about 2500 lf of pipe by the open cut and directional drill method. Pipe was installed on Maryland, Utah, North Lake, Beach and St. Mary’s Roads. Contractor will continue on Beach and Maryland next week.

Transmission

Contractor installed about 1450 lf of pipe by the open cut and directional drill method, 1000 lf of the 1450 was the last large drill shot on RT 8. Contractor will continue with open cut along RT 8 to meet up with the drill shots and make the tie in to the previously drilled pipe.