STEP Two rain days for the week: One STEP Tank was installed on Queen Anne Road by the contractor this week. The contractor also installed 5 electric meter replacements / modifications on Oregon Road. The contractor completed one house connection to the Public Sewer… Continue Reading “SKI Project Update 2.15.19”