Day: October 4, 2019

SKI Project Update 10.4.19

STEP This week the contractor completed 8 house connections to the Public Sewer System on Claiborne and Long Point Road.  Three STEP tanks were installed by the contractor this week on Brick House and Queen Anne Road.  Four STEP assemblies with pumps were installed…