Day: October 25, 2019

SKI Project Update 10.25.19

STEP The contractor has completed 3 house connections to the Public Sewer System on Queen Anne Road. Four STEP tanks were installed on Queen Anne Road.  Three STEP assemblies with pumps were installed in addition to 135LF of 4” gravity sewer line installed to…