SKI Project Update 10.11.19 and 10.18.19

STEP During the last two weeks; The contractor completed 14 house connections to the Public Sewer System on Long Point, Brick House, Queen Anne and Romancoke Roads.  Six STEP tanks were installed on Brick House, Dorchester, Romancoke and Queen Anne Roads.  Seven STEP assemblies…