SKI Project Update 10.4.19

STEP

This week the contractor completed 8 house connections to the Public Sewer System on Claiborne and Long Point Road.  Three STEP tanks were installed by the contractor this week on Brick House and Queen Anne Road.  Four STEP assemblies with pumps were installed along with connecting three pump assemblies to previously installed STEP assemblies in addition to 354LF of 4” gravity sewer line installed to those individual homes.  The contractor completed 10 septic tank abandonments.  Eight control panels were placed by the contractor along with the installation of 1,273LF of electrical conduit and 1″ pressure sewer line.  On Wicomico Road the contractor worked on completing 6 electric meter replacements / modifications for the week.  The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue utility operations on Long Point Road; drilling 1” service lines, installing STEP tanks and house connections. Additional locations will be posted.  County staff has performed 615 pre- construction meetings and acquired 756 easements to date.

  • County staff has performed 5 post-construction meetings to date.
  • The contractor has installed 513 STEP tanks to date.
  • The contractor has connected 168 houses to the public sewer system to date.

749c4820-77dc-4531-a2a1-cb38a1533eb0a599fc08-cda6-4a07-817a-80daf79153e9

%d bloggers like this: