STEP This week the contractor completed three house connections to the Public Sewer System on Olive Branch and Harford Roads and is currently working on three additional house connections on Maryland Road and Penny Lane. The snow day on Wednesday slowed down construction for… Continue Reading “SKI Project Update 2.22.19”
STEP Two rain days for the week: One STEP Tank was installed on Queen Anne Road by the contractor this week. The contractor also installed 5 electric meter replacements / modifications on Oregon Road. The contractor completed one house connection to the Public Sewer… Continue Reading “SKI Project Update 2.15.19”
STEP One STEP Tank was installed on Cecil Road by the contractor this week. The contractor also installed 11 electric meter replacements / modifications on Oregon Road. The contractor completed two house connections to the Public Sewer System on Cecil and North Lake Roads… Continue Reading “SKI Project Update 2.8.19”
STEP The contractor installed 1 STEP Tank on N. Lake for the week. This week, the contractor installed 3 electric meter replacements / modifications on Oregon Road. The contractor completed four house connections to the Public Sewer System on Margaret Drive, Harford and Olive… Continue Reading “SKI Project Update 2.1.19”
STEP The contractor installed 2 STEP Tanks on N. Lake and Utah Road for the week. This week the contractor installed 5 electric meter replacements / modifications on Oregon Road. The contractor is working on completing two house connections to the Public Sewer System… Continue Reading “SKI Project Update 1.25.19”
STEP The contractor installed 3 STEP Tanks on Elm Street and Tennessee Road for the week. A total of 428 STEP Tanks have been installed to date. This week the contractor installed 5 electric meter replacements / modifications on Oregon Road. One control panel… Continue Reading “SKI Project Update 1.18.19”
STEP Contractor installed 8 STEP tanks on Tennessee and Romancoke Roads, Oak and Elm Street during the first two weeks of January. The contractor installed 6 electric meter replacements / modifications on Maryland and New Jersey Roads, Oak and Elm Street for the first… Continue Reading “SKI Project Update 1.11.19”
STEP Contractor installed 4 STEP tanks on Tennessee, Oregon and Romancoke Roads for the week. Total STEP tank installs 417 to date. The contractor also installed 1 bio tube (less pump) this week to a previously installed tank on Harford Road, in addition to… Continue Reading “SKI Project Update 12.28.18”
16-01 STEP Contractor installed 3 STEP tanks on Tennessee and Oregon Roads for the week. The contractor installed 5 electric meter replacements / modifications on Elm Street and Maryland Road, this week. The contractor also installed 4 bio tubes (less pump) this week in… Continue Reading “SKI Project Update 12.21.18”