SKI Schedule- Community Collection Lines SKI schedule March Open cut work on the following roads, possible detours: Carroll Road Claiborne Road Olive Branch Road Horizontal Directional Drill (HDD) will be on the following roads: Harford Road Allegany Road Margaret Drive Cecil Road Dorchester Road… Continue Reading “Project Update 03.08.17”
The SKI sewer system is coming along very well. Be sure to visit us at 9410 Romancoke Road and get your easements signed. We are coming!!!!!!!! STEP Contractor has completed installing tanks on Touhey Road and has started on Margaret. They have installed 18… Continue Reading “Project Update 03.03.17”
STEP The County acquired 9 additional easements on Margaret Drive. The contractor was preparing a water truck for testing the tanks and mobilizing to Margaret to start installing tanks on Monday 27th. Community Collection Mains The Contractor set up for Horizontal Direction Drill (HDD)… Continue Reading “Project Update 02.27.17”
Community Collection Line Horizontal Directional Drilling (HDD) for the placement of a 3-inch community main will begin on Touhey Drive starting on Thursday, February 23.
STEP Contractor has one more tank to install on Touhey. This tank will be installed on Monday, 02/20/17. The contractor will then move to Margaret Drive to start installing tanks on 02/27/17. The contractor will be using next week to complete restoration on Touhey… Continue Reading “Project Update 02.17.17”
STEP 3 pre-construction meetings were held this week and 8 easements were acquired. No tanks were installed this week, will continue to install tanks next week. Contractor has 13 more tanks to install before the end of February. Community Collection Mains Marking out tee… Continue Reading “Project Update 02.03.17”
STEP 2 tanks were installed this week. Rain slowed down progress for this week. MDE project signs have been place. Tanks continue to be installed. Community Collection Lines Still waiting on pipe delivery. MDE sign placed. Transmission main will be crossing Maryland and New… Continue Reading “Project Update 01.27.17”
STEP Contract Contractor and QAC Staff held 5 Homeowner interviews. Contractor installed 2 STEP tanks. Four tanks scheduled to be installed on Touhey Drive this week. Interviews will be continuing. … Community Collection Lines: Continuing to mark curb stop locations with wooden stakes in… Continue Reading “Project Update 01/18/17”