Category: Uncategorized

Project Update-05/15/17

The SKI Sewer Project will be staging sewer force main pipe from Matapeake School area to north of Blunt Marsh Road near the Cloisters project. Pipe will be moved on Thursday, May 18 at 1:00 pm;  there will be an active lane closure. A second… Continue Reading “Project Update-05/15/17”

Project Update- 06.16.17

STEP 4 Step Tanks were installed this week on Maryland and New Jersey Roads. Contractor will continue on these roads next week. County staff acquired 7 more easements and held 8 pre-construction meetings. We have about 63% of the total number of easements. Community… Continue Reading “Project Update- 06.16.17”

Project Update- 05.12.17

STEP 3 step tanks were installed this week, 2 on New Jersey and 1 on Maryland. The contractor has conducted pre-construction meetings with home owners on Oregon Road and plan to start installing tanks there. County staff acquired more easements, to bring the total… Continue Reading “Project Update- 05.12.17”

Project Update- April 2017

STEP For the month ending 4-30-17, the contractor has used 11% of the contract time and has installed 50 tanks to date. This equates to about 5% of the total number of tanks. Production on the tanks has ramped up now that we are… Continue Reading “Project Update- April 2017”

Project Update 04.28.17

STEP 4 tanks were placed this week on Maryland, Oak, and New Jersey. County staff also acquired 4 more easements and conducted 4 more pre-construction meetings. Community 1500 feet of pipe was installed by open cut and HDD method this week on Brick House,… Continue Reading “Project Update 04.28.17”

Project Update 04.22.17

STEP Five tanks were installed on Maryland this week. County staff also acquired three more easements which brings the total number of acquired easements to 354. This represents about 46% of the 775 homes. Staff also conducted five Homeowner pre-construction meetings. Tanks will continue… Continue Reading “Project Update 04.22.17”

Project Update 04.07.17

STEP Contractor installed 3 tanks for this week, 2 on Olive Branch and 1 on Harford Road; 5 more easements were acquired this week. County staff has been busy with homeowner questions and concerns. Community Contractor installed about 2600 feet of pipe on Dorchester, Penny, Margaret & Petinot… Continue Reading “Project Update 04.07.17”

Project Update 04.03.17

STEP No tanks were placed this week but 19 were this month. Tank production had slowed but is back up to speed. County staff have received 7 more easements and meet with 4 homeowners this week. The contractor has used about 9% of the… Continue Reading “Project Update 04.03.17”

Project Update 03.24.17

STEP The contractor installed 4 more tanks this week on Margaret Drive, Harford Road, and Petinot Drive. 10 more easements were acquired this week to bring the total to 323 to date. Contractor and County personnel also held homeowner meetings on Maryland and New… Continue Reading “Project Update 03.24.17”

Project Update 03.17.17

STEP Contractor installed 2 tanks on Margaret, one on Olive Branch, and one on Harford. We also acquired 7 more easements this week. The staff has acquired 313 easements to date, this is about 40% of the total homes to be served in phase… Continue Reading “Project Update 03.17.17”