Phase 3 Kentmorr & Queen Anne Colony: STEP tank placement began in January 2024, in the Kentmorr Community. Since that time 42 STEP tanks have been installed and connected to the public sewer. Cole Ventures is projected to have the community of Kentmorr completed… Continue Reading “Southern Kent Island Sewer Project Update May 24, 2024”
Previous (2021) work completed 33 connections 21-01 STEP On September 15, 2023 the contractor completed phase 2 STEP tank installations and sewer connections to 167 existing homes. This finalizes the public sewer connections to the 200 existing homes located in Tower Gardens. 22-02 Community Mains On… Continue Reading “SKI SEWER PROJECT UPDATE 12.12.23”
Queen Anne’s County Sanitary District will be performing routine sewer tank maintenance on your STEP System. Phase 1 – Kent Island Estates and Romancoke on the Bay. A Homeowner’s Guide to Septic Tank Effluent (STEP) Systems system. County sanitary utility workers will be… Continue Reading “SKI PHASE 1 (KIE & ROB) information, SKI Sewer 21-01 STEP and SKI Sewer 22-02 Community Mains Update May & June 2023”
Previous (2021) work completed 33 connections 21-01 STEP (200 Existing Homes) Progress for the months of March and April 2023, SKI Sewer Project Phase 2 – Tower Gardens. The contractor completed installing 23 STEP tanks and connecting 24 houses to Public Sewer. Those installs… Continue Reading “SKI STEP Phase 2 & COMMUNITY MAIN SEWER Phase 3 PROJECT UPDATE 4.30.23”
Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of January and February 2023, SKI Sewer Project Phase 2- Tower Gardens. The contractor completed installing 25 STEP tanks and 25 house connections to Public Sewer. Those installs and connections completed Drovers… Continue Reading “SKI STEP Sewer Project Update 2.28.23”
16-01 STEP – RECAP Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of November and December 2022, SKI sewer Project Phase 2 – Tower Gardens. The contractor continues public sewer utility operations on Beachside Drive and on December 1st began… Continue Reading “SKI Sewer Project Update 12.31.22”
Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of September and October 2022, SKI sewer Project Phase 2 – Tower Gardens. The contractor continues public sewer utility operations on Beachside Drive. 20 STEP tanks were installed along with the completion… Continue Reading “SKI Sewer Project Update 10.31.22”
22-02 Phase 3 Community Mains For the months of July and August 2022 the contractor has drilled and installed pipe for the community mains in the Kentmorr sub-division. The contractor has moved to Queens Colony High Road to drill and install 6” pipe for… Continue Reading “SKI Sewer Project Update 8.31.22”
21-01 Phase 2 STEP Previous (2021) work completed 33 connections. For the month of August 2022 SKI Sewer Project Phase 2 Tower Gardens the contractor installed 15 STEP tanks and completed 13 house connections on North Lake and Beachside Drive, in addition to other… Continue Reading “SKI Sewer Project Update 8.31.2022”
Previous (2021) work completed 33 connections. 21-01 STEP For the month of July 2022 SKI Sewer Project Phase 2 Tower Gardens the contractor installed 9 STEP tanks and completed 9 house connections on North Lake Drive. Along with other utility requirements and yard restorations… Continue Reading “SKI Project update 7.31.22”