Project Update 03.16.18

STEP Contractor installed three step tanks on Talbot Road and four 1” inch drill shots on Maryland Road.  County staff has acquired 675 easements (87%) to date.  Contractor will continue setting tanks next week on Talbot.  Door hangers are being placed on Wicomico Road… Continue Reading “Project Update 03.16.18”

Project Update 03.09.18

STEP Contractor installed 1” service lines to tanks that were previously installed on Maryland Road this week. They also worked on some of the OP roads filling pot holes. Contractor will continue next week with tank installs and service lines on Maryland and Touhey.… Continue Reading “Project Update 03.09.18”

Project Update 03.02.18

STEP Contractor installed 5 tanks for the month and ran 1403lf of 1” pressure pipe from 13 previously installed tanks to the street. This brings the number of tanks installed to 225 to date. This equates to 28% of the contract price paid out… Continue Reading “Project Update 03.02.18”

Project Update 02.16.18

STEP Contractor installed service lines from previously installed tanks to the street on Margaret Drive. The Contractor, Community Roads Association and the County have been working in a joint venture to make the private roads more passable. County staff have acquired 661 easements to… Continue Reading “Project Update 02.16.18”

Project Update 02.09.18

STEP Contractor set one tank this week on Worcester Road. They also started drilling service connections on Margaret Road. They will continue on Margaret Road next week. Community Contractor installed service connection on Ackerman Road. Will continue to finish up on Ackerman next week.  Transmission… Continue Reading “Project Update 02.09.18”

Project Update 02.02.18

STEP The contractor installed 12 tanks for the month and ran 450lf of 1” service line to several houses on Touhey Drive. This brings the total contract completed to about 27% with about 29% of the contract time used. County staff has acquired 654… Continue Reading “Project Update 02.02.18”

Project Update 01.26.18

STEP The contractor installed 3 tanks for the week. Wet conditions have slowed the tank installs; it has made the restoration efforts rough. On properties that the tank installs are still rough graded, please be patient, the contractor will restore your property correctly. Tank… Continue Reading “Project Update 01.26.18”

Project Update 01.12.18

STEP The contractor installed 3 tanks on St Mary’s and Utah roads. They also installed 154lf of 1” service lines to tanks previously installed on Touhey Road. County staff have acquired 649 easements to date and have performed 261 pre-construction meetings with homeowners. The… Continue Reading “Project Update 01.12.18”

Project Update 01.05.18

The contractors were only able to work one day this week due to holiday schedule and inclement weather. STEP… Next week, weather permitting, they will install tanks on Utah and St. Mary’s and continue direction drilling service lines on Touhey. Community Continue service laterals… Continue Reading “Project Update 01.05.18”

SKI Project Report- December

STEP Contractor installed 14 tanks for the month of December. That makes a total of 208 tanks installed to date. The contractor also started installing the 1” service line from the street to some of the previously installed tanks on Touhey drive. County staff… Continue Reading “SKI Project Report- December”