Step Contractor installed 4 tanks for the week on Wicomico, Kent and Dorchester Roads. They also ran 238lf of 1″ service lines from the street to previously installed tanks. The contractor also changed out 11 electrical meter boxes on Long Point and Allegany. Electric… Continue Reading “SKI PROJECT UPDATE 5.25.18”
Step – Community – Transmission RAIN Over 6.5 inches of rain was recorded at the SKI office from Monday morning thru Friday noon. No work by the contractors this week. Early next week not looking much better before mid-week.
Step Contractor installed 5 step tanks for the week on Wicomico. They also ran about 565lf 1″ service lines from the property line to the step tank. The contractor also changed out 10 electrical meter boxes on Allegany. Electrical Meter Replace/ Electric Meter Modification… Continue Reading “Project Update 5.11.18”
STEP Contractor installed 17 tanks for the month on Wicomico and Talbot Roads. They also installed about 2400 lf of 1″ service line from the street to previously installed tanks on New Jersey and Oak Street. The contractor also changed out or modified 25… Continue Reading “SKI Project Update 5.04.18”
STEP Contractor installed 5 tanks on Talbot and Wicomico Roads for the week. The contractor also installed about 590lf of 1” service line from previously installed tanks to the street on Oregon Road. Contractor will continue installing tanks on Wicomico next week. Electrical connections… Continue Reading “Project Update 04.27.18”
16-01 Contractor installed 5 tanks for the week on Wicomico Road. They also ran about 500lf of 1″ service lines from the street to previously installed tanks. The contractor also changed out 6 electrical meter boxes on New Jersey. Electric meter modifications / change… Continue Reading “SKI Project Update 4.20.18”
STEP Contractor started with the electric meter modification this week on New Jersey. Four meter pans were changed out and one was modified. All 5 now have the sewer disconnect breaker installed on the side or bottom of the meter can. The contractor also… Continue Reading “Project update 4.13.18”
STEP Contractor installed 9 tanks on Talbot and Worcester Roads for the month. The total number of tanks installed to date 234. They also installed approximately 1300 lf of 1″ service line from previously installed tanks to the road on Maryland Road. Contractor has… Continue Reading “Project Update 4.6.18”
STEP Contractor installed 2 tanks on Talbot Road this week. They also installed 1” service lines to previously installed tanks on Maryland Road. Tanks will continue to be installed on Talbot next week. County staff have acquired 682 easements to date and performed 281… Continue Reading “Project Update 03.29.18”
STEP Contractor installed one step tank on Talbot RD. Inclement weather has slowed down progress for the week. County staff has aquired 679 easements(88%) to date. Contractor to continue installing tanks on Talbot. COMMUNITY Contractor placed ten curb stops on Baltimore Road for the… Continue Reading “Project Update 03.23.18”