Category: Uncategorized

SKI Project Update 08.06.18

STEP The contractor installed 21 STEP tanks for the month. They also replaced or modified 25 electric meters, and directional drilled 2561lf of 1” service line to previously installed tanks. The work completed to date, equates to about 35% of the total job with… Continue Reading “SKI Project Update 08.06.18”

SKI Project Update 7.27.18

Project was delayed due to an average of 6” of rainfall this week in Southern Kent Island. Step The contractor installed 3 STEP tanks for the week on Pennick and Ackerman Drive.  They also drilled 304lf of 1″ pressure sewer line on Utah Road. … Continue Reading “SKI Project Update 7.27.18”

SKI Project Update 7.20.18

Step The contractor installed 5 step tanks for the week on Pennick Drive, Harford and Olive Branch Roads.  They also drilled 515lf of 1” pressure sewer line on Utah Road.  The contractor did yard restorations on Pennick Drive, Harford and Olive Branch Roads.  The… Continue Reading “SKI Project Update 7.20.18”

SKI Project Update 7.13.18

Step The contractor installed 7 step tanks for the week on Pennick Drive, Olive Branch Road. They also drilled 917lf of 1″ pressure sewer line on Utah Road. The contractor did yard restorations on Pennick Drive and Olive Branch Road. The contractor will continue… Continue Reading “SKI Project Update 7.13.18”

SKI Project Update 7.6.18

16-01 The contractor installed 5 step tanks for the week on Pennick Drive, Olive Branch and Long Point Roads.  They also drilled 735lf of 1” pressure sewer line on Utah Road.   The contractor will continue drill shots on Utah Road next week.  County Staff… Continue Reading “SKI Project Update 7.6.18”

SKI Project Update 6.29.18

16-01 Step Contractor installed 7 step tanks for the week on Wicomico, Carroll and Pennick Roads. They also drilled 695lf of 1″ pressure sewer line from the property line to the step tanks.  Long Point and Romancoke Roads Electric Meter Installs will begin next… Continue Reading “SKI Project Update 6.29.18”

SKI Project Update 6.22.18

Step Contractor installed 7 step tanks for the week on Baltimore, Romancoke and Wicomico Roads. They also drilled 493lf of 1″ pressure sewer line from the property line to the step tanks on Tennessee Road. The Electric meter installs will begin again next week… Continue Reading “SKI Project Update 6.22.18”

SKI Project Update 6.15.18

  Step The contractor installed 5 step tanks for the week on Wicomico, Dorchester and Baltimore Roads.  They also drilled 629lf of 1″ pressure sewer line from the property line to the step tanks.  The contractor installed 6 electric meter replace / modification on… Continue Reading “SKI Project Update 6.15.18”

SKI Project Update May 2018

May rain fall recorded at the SKI office was over 10 inches.   STEP Contractor had a productive month in spite of the rain. The contractor installed 17 STEP tanks on Wicomico, Washington, and Kent Roads. They installed 35 Bio-tubes in previously installed tanks… Continue Reading “SKI Project Update May 2018”

SKI Project Update 6.1.18

Step Contractor installed 5 tanks for the week on Wicomico, Kent and Washington Roads.  They also ran 483lf of 1″ service lines from the street to previously installed tanks with bio-tube less pump.  The contractor installed 5 electric meter replace and 1 electric meter… Continue Reading “SKI Project Update 6.1.18”