Project Update 12.21.17

Please be advised that there will be no work on the Southern Kent Island sewer project from the end of the day on 12/22/17 thru 1/02/2018. County staff will be on site, if you have any questions, on 12/26-27-28-29/2017 and again with a full… Continue Reading “Project Update 12.21.17”

Project Update 12.15.17

STEP Contractor installed 6 tanks for the week on South Carolina. They plan to set tanks on Tennessee and North Lake next week. The contractor will also start installing service line pipe from the previously installed tanks to the street, next week on Touhey,… Continue Reading “Project Update 12.15.17”

Project Update 12.11.17

STEP 6 tanks were placed this week on Virginia Road; contractor will continue installing tanks on South Carolina next week. County staff have performed 258 pre-construction meetings with homeowners, and have acquired 640 (82%) easements to date. Community Contractor installed about 130lf of pipe… Continue Reading “Project Update 12.11.17”

SKI Project Report- November 2017

STEP Contractor installed 25 tanks for the month on Virginia, Elm, and North Lake Roads; installation will continue on these roads next week. To date the contractor has installed 194 tanks, about 26% of the total contract and they have used about 25% of… Continue Reading “SKI Project Report- November 2017”

Project Update 11.17.17

STEP Contractor installed 6 tanks for the week on North Lake Road. They plan to continue with tank installs on Virginia Road next week. County staff has performed 242 pre-construction meetings with homeowners and have acquired 629 easements to date.   Community Contractor installed… Continue Reading “Project Update 11.17.17”

Project Update 11.10.2017

Step Contractor installed 5 tanks for the week on Virginia and Bay Drive. County staff has acquired 622 easements to date and has held 236 pre-construction meetings with homeowners. The contractor will continue installing tanks on North Lake, Elm, and Virginia next week. The… Continue Reading “Project Update 11.10.2017”

Project Update 11.03.17

STEP Contractor installed 5 tanks for the week on Utah Road totaling 173 Tanks set to date.  Contractor will continue on Virginia and Bay Roads next week.  County staff have acquired 80% (616) of 775 easements required . County staff has conducted 230 pre-construction meetings… Continue Reading “Project Update 11.03.17”

Project Update 10.27.17

STEP Contractor installed 9 tanks for the week on Utah Road, contractor will continue on Utah next week. County staff has acquired 603 easements and have conducted 221 pre-construction meetings to date. Community Contractor installed 233 lf and is continuing to install clean-outs and… Continue Reading “Project Update 10.27.17”

Project Update 10.20.17

STEP Contractor installed 6 tanks for the week on Utah Road. Contractor will continue on Utah next week. County staff has acquired 759 Right of Entries, 596 easements and have conducted 214 pre-construction meeting to date. Community Contractor is continuing to install clean-outs and… Continue Reading “Project Update 10.20.17”

Project Update 10.13.17

  STEP Contractor installed 5 tanks for the week on Utah Road, they will continue on Utah next week. We are still expecting to see the second tank crew sometime this month. County staff has acquired 759 right of entries, 592 easements and have… Continue Reading “Project Update 10.13.17”