STEP Contractor installed 19 tanks for the month. That brings the total tanks installed, as of 9-30-17, to 142. That equals about 23% of the contract amount paid to date with 21% of the contract time used. The contractor will be installing tanks on… Continue Reading “SKI Project Report- September”
STEP This week six tanks were set on Tennessee and Utah. The contractor will continue on Utah and South Carolina next week. County staff has acquired 585 easements to date; this brings the total to 75% of the amount required. Community Contractor installed about… Continue Reading “Project Update 09.29.17”
STEP This week five tanks were set on Tennessee Road; contractor will continue on Tennessee next week. County staff has acquired 577 easements to date. That is about 74% Community Contractor installed about 150lf of pipe by the open cut method on Tennessee Road.… Continue Reading “Project Update 09.22.17”
STEP Tennessee Road- The contractor set 4 tanks this week and will continue installing there next week. County staff has acquired 575 easements to date. Community The past week was spent filling the community main lines with water for pressure testing. The contractor was… Continue Reading “Project Update 09.15.17”
STEP The contractor installed 20 tanks for the month. That brings the total number of tanks installed to 123, or 16%. The contractor has used about 19% of the contractor time. County staff continues to acquire easements and answer questions at the SKI office.… Continue Reading “Project Update 09.08.17”
16-01 STEP: 4 tanks were set this week on Oregon, South Carolina, and Elm Street. Contractor to continue on South Carolina and Oregon area. 16-02 Community: Contractor installed 1400 lf of pipe by the open cut and HDD method this week. Pipe was installed on Tennessee… Continue Reading “PROJECT UPDATE 08.28.17”
STEP Office staff acquired 3 more easements this week for a total of 568 which equal 73 % of the required easements for the project. Contractor installed four tanks on Oregon, Elm and South Carolina Roads. The contractor and Project representative attended 4 more… Continue Reading “Project Update 08.25.17”
STEP Contractor installed 6 tanks this week on Oregon Road. County staff received 4 more easements. This brings the total easements collected to 565. This is 73% of the total number of easements. Next week, the contractor is planning on installing tanks on Oregon,… Continue Reading “Project Update 08.18.17”
STEP Two tanks were installed this week on Tennessee Road by the contractor. Contractor will continue with tank installations on Oregon Road next week. County staff obtained 8 more easements bringing the total to 561 or 72% of all the easements. Community The contractor… Continue Reading “Project Update- 08.11.17”